Location & Programme

Proposed Pettywell Solar Farm Location

Why Here?

What has been assessed?

The permitted planning application for the site included assessment and consideration of the following topics:

  • Landscape and visual factors
  • Ecology
  • Archaeology and cultural heritage
  • Traffic and transport
  • Noise
  • Agricultural farmland
  • Flood risk and drainage
  • Fire risk
  • Glint and glare
  • Use of alternative sites

The Cable Route planning application will include assessment and consideration of the following topics:

  • Ecology and Trees
  • Historic Environment
  • Traffic and transport
  • Flood risk

The Project Timeline

November 2024

Site planning application submitted

April 2025

Site planning permission granted 

July 2026

Site Archaeological Trenching Investigations

August 2026

Cable Route and Section 73 planning applications submitted

Early/mid 2027

Construction commences

Early 2028

Construction completed & site becomes operational